Thank you for your patience and understanding as we move through the phases of the Killam Library Deep Energy Retrofit Project.
The current phase of the project requires closures on the fourth floor of the Killam Library including the Grad Pad and quiet study rooms. Closures will happen in 3 stages and were scheduled to avoid closing during both the December and April exam periods.
Phase 4-1: Closed for Construction November 1 – January 24
- Book stacks
- Study carrels
Phase 4-2: Closed for Construction December 4 – January 3
- Classroom 4106
Phase 4-3: Closed for Construction January 20– March 31
- Grad Pad
- Quiet study rooms
- Atrium seating
- Washrooms
Alternative seating for phase 4-3:Â the study carrels that run along the perimeter of the book stacks are available during this time.
Recent News
- Job postings
- Seeking participants for a research study on medication abortion
- Year‑end deadline for Student Aid Requisitions
- University Ave sidewalk near McCain
- Knee pain study needs participants
- Job postings
- Inventory Blowout at the Dal Bookstore
- Barbershop + Salonshop Talk