Killam retrofit update: Fourth floor closures

Posted by Dal Libraries on October 24, 2024 in Facilities Management

Thank you for your patience and understanding as we move through the phases of the Killam Library Deep Energy Retrofit Project.

The next phase of the project requires closures on the fourth floor of the Killam Library including the Grad Pad and quiet study rooms. Closures will happen in 3 stages and are scheduled to avoid closing during both the December and April exam periods.

Phase 4-1: Closed for Construction November 1 – January 24

  • Book stacks
  • Study carrels

Phase 4-2: Closed for Construction December 4 – January 3

  • Classroom 4106

Phase 4-3: Closed for Construction January 25– March 31

  • Grad Pad
  • Quiet study rooms
  • Atrium seating
  • Washrooms

Alternative seating for phase 4-3: the study carrels that run along the perimeter of the book stacks are available during this time.